Five Things You Should Know when Securing Lien Rights in Arizona

Five Things You Should Know when Securing Lien Rights in Arizona

I recently learned a bit about Arizona’s 5 Cs: copper, cattle, cotton, citrus and climate. Although today’s post doesn’t have the catchy 5-C-alliteration, it does list 5 important facts about securing mechanic’s lien rights in Arizona.

#1: Arizona Preliminary 20 Day Notice

Arizona, like most states, requires potential lien claimants to serve a preliminary notice. All those furnishing materials or services must serve the notice upon the owner, prime contractor, construction lender and your customer within 20 days from first furnishing.

Did you miss the 20 day deadline? You can serve the notice late, however if/when you proceed with the mechanic’s lien, the lien will only be effective for furnishings provided 20 days prior to serving the notice and for subsequent furnishings.

ProTip: Make sure your service of the notice meets the parameters within Arizona’s statute: 33-992.01. F. The notice or notices required by this section may be given by mailing the notice by first class mail sent with a certificate of mailing, registered or certified mail, postage prepaid in all cases, addressed to the person to whom notice is to be given at the person’s residence or business address. Service is complete at the time of the deposit of notice in the mail.

#2: You May Need to Amend Your Preliminary Notice

There are two common events that may warrant an amended preliminary notice. First, if the owner receives a copy of your notice and discovers the information within the notice is incorrect, he has 10 days from receipt of your notice to provide you with the correct information. Once you receive the corrected information, you then have 30 days to amend and resend your notice.

The second reason for amending a notice would be an increase in your contract amount. You may have the best estimator on the planet, but some projects (OK, perhaps most projects) will require more materials and/or services. In the event your contract amount increases by 20% or more, serve an amended preliminary notice.

Did You Know? To maintain compliance with Arizona statute, your contract amount must appear on the preliminary notice.

#3: File Your Arizona Mechanic’s Lien

The Arizona mechanic’s lien deadline is based upon the date of project completion. Lien claimants must file the lien within 120 days from completion of the project, or within 60 days from the recording of a notice of completion. As a best practice, serve all parties with a copy of the lien, but minimally, you will need to serve a copy of the lien upon the owner.

Frequently, the date of project completion is unknown to subcontractors and suppliers. Therefore, we recommend conservatively calculating your deadline based on your last furnishing date (i.e. as a best practice, file your lien within 90 days from last furnishing).

#4: Arizona is Full Balance

There are full balance lien states and unpaid balance lien states. Fortunately, Arizona is a full balance lien state. This means the lien is enforceable for the full amount owed, regardless of payments made by the owner.

#5: Suit to Enforce Lien

If you have filed a mechanic’s lien, and have yet to receive payment, your next step would be to file suit to enforce your lien. According to Arizona’s statute, claimants must proceed with lien enforcement within 6 months from the filing of the lien.

33-998. Limitation of action to foreclose lien
A. A lien granted under the provisions of this article shall not continue for a longer period than six months after it is recorded, unless action is brought within that period to enforce the lien and a notice of pendency of action is recorded pursuant to section 12-1191 in the office of the county recorder in the county where the property is located. If a lien claimant is made a party defendant to an action brought by another lien claimant, the filing within such period of six months of an answer or cross-claim asserting the lien shall be deemed the commencement of an action within the meaning of this section.

Bonus: Stop Notice

In addition to the filing of a mechanic’s lien, unpaid parties may seek recovery through the service of a stop notice. A stop notice can obligate the lender to withhold sufficient funds to cover unpaid amounts. The stop notice should be served upon the owner and lender within 120 days from completion of the project, within 60 days from the recording of a notice of completion or within 30 days from written demand by the owner or lender.

Do you need to secure your rights for a project in Arizona? Or, do you have questions about mechanic’s liens? Contact us today!

Most Recent Resources

Blog

You Should Try a Collection Agency Before Writing Off Past-Due Accounts

NCS Attorney, Michelle Gerred discusses why you should use a contingent collection service before writing off bad debt.
Read More
video icon
Video

NCS Credit's Year-End Collection Tips 2024

Hard to believe 2024 is nearly over! As you prepare your A/R for year-end, let's review a few collection tips to help you close 2024 and prepare for 2025.

Read More
conference
Tradeshow

ELFA Credit & Collections Management Conference

The Credit and Collections Management Conference & Exhibition addresses the new and emerging issues relevant to credit and collections professionals and emerging professionals in the equipment finance industry.
Read More